FERC Grid Plan Backtrack Draws Legal Fire Over Cost Allocation Changes

0
26

“That recent FERC order remains subject to review by both FERC and this court, which several respondent-intervenors have sought,” the co-ops emphasized. “And the order does not come close to granting the full relief petitioners seek here, as the tariff amendment established a waiver process that would govern not just existing facilities, but future facilities.”

FERC Grid Plan Backtrack : Co-ops Say FERC’s Concerns Are Unfounded

Once the question of standing is set aside, the co-ops argue that FERC’s rationale for reversing the grid plan still falls flat. The agency’s concerns about discriminatory project cost allocation and a lack of transparency, they say, are insufficient to justify a reinstatement of the previous cost allocation structure, which they view as unfair.

“FERC also continues to ignore the fact that it rejected precisely the same discrimination and transparency concerns the first time around — and did so on the basis of modifications that the commission itself directed to address those very concerns,” the co-ops wrote.

Signup for the USA Herald exclusive Newsletter

Background on the FERC Grid Plan Backtrack

The dispute has its roots in SPP’s proposal to create a waiver that would allow its board to decide, on a case-by-case basis, whether to distribute the costs of byway facilities—mutually beneficial transmission projects ranging from 100 kilovolts to 300 kilovolts—across the entire region. This plan was intended to address the increased development of wind energy projects within the wind-rich areas of the SPP grid in the central U.S., with power primarily being sent to areas of higher electricity demand.